Do I need to request a final landscape walk through on site prior to obtaining a certificate of occupancy?

Yes, the landscape contractor should schedule a final landscape walk through on site with landscape architect and the Public Works Inspector.  If a punch list is created time will be provided for the contractor to complete or correct any items or deficiencies that differ from the approved plan. Once there are no further outstanding punch-list items, the landscape architect shall submit a landscape certificate to the City which states the landscape has been installed per plan.  At that point the city Public Works Inspector may sign off the certificate of occupancy for landscaping.