CIP Current Projects

ADA Ramp Replacement/Sidewalk In-Fill

New sidewalk, curb and gutter, and pedestrian ramps at various locations throughout the City. One new location has been specifically identified for improvements: (Tremont St).

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project#: CIP17-00006

Program: Transnet

Current Phase: Design

Recent Update: Construction for the Tremont Corridor Sidewalk In-Fill began Phase 1 on November 15th, 2021.

Duration: Ongoing


ADA Self Evaluation and Transition Plan 

In keeping with its ongoing efforts to serve all members of the public, the City of Oceanside is updating its Americans with Disabilities Act (ADA) transition plan and self-evaluation. The accessibility plan provides a comprehensive plan for accessibility for persons with disabilities to City facilities, programs, services, and events. 

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project#: CIP21-00014

Program:

Current Phase: In-Process

Duration: Project began August 2021, with anticipated finish in August 2022.

Recent Update: The City is seeking input from the community and organizations assisting people with disabilities. Your feedback will assist in addressing and prioritizing current and future accessibility needs. The surveys are open for input until November 30, 2021 and includes a drop-down menu to take in several languages.

Link to Online Survey:

Survey for public input

Survey for Organizations Representing People with Disabilities

Your comments and opinions are important to us and will provide valuable information regarding how the City can better serve those with disabilities.  Thank you for your time!

Link to More ADA Information

City of Oceanside ADA information and contact  


Prince Memorial Skatepark Improvement

Facility Improvements including a new restroom facility and drinking fountain.

Project Manager: Kymberly Laubach, (760) 435-3534 or KLaubach@oceansideca.org

Project #: CIP21-00017

Program: Parks

Current Phase: Design

Recent Update:  Green Flush Restroom has been procured and preliminary engineering drawings have been reviewed and approved by City Staff. The RFP for Improvement Plans for the water and electrical lines have been prepared and advertised.

Duration: Began August 2021 and estimated completion date is Summer 2022  


Annual Overlay FY20-21

The project provides asphalt overlay of City streets.  Street selections are made based on computerized pavement management system information, staff's review to determine the high priorities for restoration, and citizen's reports of deteriorating street conditions.  This project is funded in part by Measure X.

FY20-21 Overlay and Slurry Seal Location Exhibits

Full Depth Reclamation (FDR) Process:

https://www.youtube.com/watch?v=c-oMzqB0MS0

https://www.youtube.com/watch?v=mWtDOB5n7tI

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project#: CIP21-00003

Program: SB-1, TransNet, Measure X

Current Phase: Construction.

Recent Update: Project is currently under construction.

Duration: Work Commenced July 2021.  


Annual Storm Drain Maintenance

Installation of new storm drain facilities including devices required to comply with the State Trash amendment. Replacement of failing CMP pipes throughout the City.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP20-00006

Program: SB-1

Current Phase: PSR

Recent Update: With the exception of a few materials still awaiting shipping, contractor has completed the installation of the trash capture devices around the City. Award of Contract to begin for Todd Street Slope Repair.

Duration: Annual - Ongoing


Beach Access at Neptune

Project Manager: Jonathan Smith (Consultant), (760) 435-3518 or JGSmith@oceansideca.org

Project #: CIP18-00020

Program: Municipal Buildings

Current Phase: Construction

Recent Update: Completed construction of the new foundation and began reconstruction of the stairs.

Duration: Estimated Completion Winter 2021/2022


Beachfront Improvements

Please visit the Beachfront Improvements page for more details and updates.

New construction and building renovations to include various City beach operations and public facilities within the Pier Amphitheater area.  This project is funded in part by Measure X.

Project Manager: Darra Woods, (760) 435-5094 or Dwoods@oceansideca.org

Project #: CIP19-00023

Program: Municipal Buildings

Current Phase: Construction

Recent Update: Construction of the restrooms and maintenance building is ongoing.

Duration: Began April 2020, with target completion of Winter 2021


Beachfront Improvement Feasibility Study - Phase 2

Please visit the Beachfront Improvements Feasibility Study - Phase 2 webpage for more details and updates.

Phase II of the Beachfront Improvement Feasibility Study explores potential improvements to the Junior Seau Beach Community Center, Junior Seau Pier Amphitheater/ Bandshell, and the pier plaza and public spaces in between.

Project Manager: Darra Woods, (760) 435-5094 or Dwoods@oceansideca.org

Project #: CIP21-00006

Program: Community Facilities

Current Phase: Study

Recent Update: Please visit the Beachfront Improvement Feasibility Study – Phase II page for more details and updates.

Duration: Began February 2021, with target completion of January 2022


Brooks Street - ADA

 

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP21-00007

Program: 

Current Phase: Design

Recent Update: Notified SD County of proposed project which lies within old landfill limits. Plans & specification are at 70%.

Duration: Began April 2021, with target completion of Spring 2022 


Buccaneer Beach restroom

Design for new beach restroom facility at Buccaneer Park.  This project is funded in part by Measure X.

Project Manager: Jonathan Smith, (760) 435-3518 or JGSmith@oceansideca.org

Project #: CIP19-00017

Program: Measure X

Current Phase: PSR

Recent Update: Completed three (3) draft conceptual designs for the new restroom building. Present the restroom conceptual designs and the results of the survey at a community outreach meeting.

Duration: Began October 2019, with target completion of Winter 2023


Buccaneer Park Facilities Study

This is a project study review of the aging facilities at Buccaneer Park. Recommendations will contain funding requirements for improvements. Remodel of the park restroom, picnic facility and other park amenities.  This project is funded in part by Measure X.

Project Manager:  Jonathan Smith, (760) 435-3518 or JGSmith@oceansideca.org  

Project webpage: Buccaneer Park Improvements

Project #: CIP11-00055

Program: Parks

Current Phase: PSR

Recent Update: The 4th Workshop for the re-visioning will be held on Tuesday May 3rd. See flyer below for details.

Buccaneer Park Flyer - 4th Workshop - English

Buccaneer Park Flyer - 4th Workshop - Spanish

Duration: Began October 2011, target completion of April 2021


Calavera Creek Crossing Design

Modernization and Improvements for areas within Calavera Creek

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org

Project #: CIP21-00010

Program: Parks

Current Phase: Design

Recent Update: Based on available funds, the project scope has changed and the City is in-progress to get a consultant to prepare design documents for the new project scope.

Duration: Start November 2021, with target completion of Fall 2022.


Citywide Traffic Signal Upgrades HSIP 2019

Various signal improvements.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP20-00002

Program: Grant

Current Phase: Design

Recent Update: Completed site investigations, preliminary cost estimates, and 75% plans

Duration: Began May 2020, with target completion of Spring 2022


Civic Center Fuel Storage 

Installation of a new fuel tank for the civic center generator.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP18-00016

Program: Municipal Buildings

Current Phase: Design

Recent Update: Notified the Consultant of the comments received by the various departments.

Duration: Start October 2018, with target completion of 2021


Cleveland Storm Drain 

Upgrade of storm drain. Cleveland from Seagaze to Surfrider and Surfrider to the Ocean. May include parallel line from Civic Center to Surfrider.

Project Manager: Jonathan Smith, (760) 435-3518 or JGSmith@oceansideca.org

Project #: CIP17-00007

Program: Drainage

Current Phase: Design

Recent Update: Met with the CCC to discuss the permit for the storm drain outfall on beach at Surfrider Way. Acquired NCTD approval of Utility Crossing Agreement.

Duration: Start June 2017, with target completion of Spring 2023


Coast Highway Bridge Replacement

This is a Federally funded project to replace the bridge that carries Coast Hwy over the San Luis Rey River. Caltrans will be the partner agency, with financing through the HBRRP (Highway Bridge Rehabilitation and Replacement Program.)

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP11-00030

Program: Transnet

Current Phase: Design

Recent Update: Staff confirmed California Transportation Commission will make Prop B funds for seismic retrofit available to replace portion of lost State Toll Credit funds. Loss of funds due to revised roadway classification.

Duration: Start September 2011, with target completion of Fall 2026


Coast Highway Corridor Design

Project to install separated bike lanes between Oceanside Boulevard and Morse Street.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP20-00012

Program: Transnet

Current Phase: Under Review

Recent Update: Staff is preparing a draft RFP for consultant services to prepare plans, specifications, and estimates for a phased project.

Duration: Began October 2020, with target completion TBD


Coastal Rail Trail Design 

Project for the design of the Coastal Rail Trail for the section between Oceanside Blvd and Morse Street.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP16-00011

Program: Transnet

Current Phase: Design

Recent Update: Circulated the MND document for public review. Addressed comments. Prepared the final MND.

Duration: Began August 2016, target completion TBD  


 

College Between Waring & Old Grove Design

Thoroughfare Widening project - Corridor Right-of-way improvements to provide congestion relief.

See more project and meeting info on the College Boulevard Roadway Widening Project Flyer.
(NOTE: The April 19th Meeting has been cancelled and will be rescheduled.)

Take part in the College Blvd Public Survey.

College Blvd Public Survey (Spanish)

Project Manager: Jonathan Smith, (760) 435-3518 or JGSmith@oceansideca.org

Project #: CIP19-00019

Program: Thoroughfare

Current Phase: Design

Recent Update: Community outreach ongoing. See flyer and survey above.

Duration: Began December 2020, target completion of Winter 2022 for Design and Fall 2023 for Construction

 

Dog Facilities Study

This project seeks to determine which parks can best accommodate Dog Facilities within the City.

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org

Project #: CIP21-00010

Program: Parks

Current Phase: Study

Recent Update: The Dog Facilities Study has been drafted and is currently being routed internally for review.

Duration: Start May 2021, with target completion of Winter 2021/2022


Douglas Bridge Seismic Retrofit

This is a federally funded project to retrofit the bridge that carries Douglas Drive over the San Luis Rey River to meet earthquake design standards.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP11-00010

Program: Transnet

Current Phase: Design

Recent Update: Preliminary Environmental Study (Caltrans PES for NEPA) complete, signed by City staff, and pending final signature by Caltrans.

Duration: Start September 2011, with target completion of Fall 2026


Douglas Drive Median

Median on Douglas Dr between 300 feet south of Westport Dr and 250 feet north of Festival Drive.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP16-00010

Program: Transnet

Current Phase: Construction

Recent Update: The project NTP was issued 7/8/21 and construction commenced 7/19/21. Construction is substantially completed.

Duration: Start August 2016, with target completion of Fall 2021  


 

Fire Mountain Utility Undergrounding

City participation in a "Section 20B" underground utility conversion with Eternal Hills Cemetery to remove overhead poles and wires along Fire Mountain between El Camino Real and the City reservoir.

Project Manager: Randall Bliss, (949) 536-2511 or randall.bliss@weareharris.com

Project #: CIP13-00017

Program: Miscellaneous City Capital

Current Phase: Design

Recent Update: SDG&E design engineer began preparing utility plans and specifications.

Duration: Project Start August 2013, with target completion TBD


Fiber Optic to Fire Station No. 6

Replacement of the current microwave radio signal, susceptible to wind movement and tree growth into its line of sight, with fiber optic system to provide network stability.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP19-00015

Program: Miscellaneous City Capital

Current Phase: On-Hold

Recent Update: Sent an RFP to contractor working on Traffic Signal at San Ramon and RDO to obtain the cost to run conduit across two intersections and perform an inspection of existing conduit that runs between COC and Fire Station #6.

Duration: Project Start October 2019


Fire Station No1/EOC Design

Measure X funds contribution toward design of a new Fire Station #1 at 602 Civic Center Drive which will require relocation of Code Enforcement offices.

Project Manager: Brian Thomas, (760) 435-5074 or BThomas@oceansideca.org

Project #: CIP19-00012

Program: Measure X

Current Phase: Design

Duration: Start October 2019, with target completion of Fall 2023

Recent Update:  Staff presented entitlement level plan at 10/25/21 Planning Commission. Staff advertised the construction documents for contractor prequalification.


Fire Station #4 Rehabilitation Phase 2

Repair deficiencies in the sleeping quarters, showers, bathrooms and hallways not addressed as part of Phase 1 improvements.

Project Manager: Brian Thomas, (760) 435-5074 or BThomas@oceansideca.org

Project #: CIP19-00024

Program: Municipal Buildings

Current Phase: Design

Recent Update: Phase 2 schematic drawing completed to 90% level.

Duration: Project Began October 2019, target completion of late Spring 2022


Fire Station #8 Design

Repair deficiencies in the sleeping quarters, showers, bathrooms and hallways not addressed as part of Phase 1 improvements.

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org  

Project #: CIP21-00019

Program: Municipal Buildings

Current Phase: Under Review

Recent Update: RFP prepared and advertised. Addressed RFP questions. Received 8 proposals.

Duration: Project Began October 2019, target completion of late Fall 2022


Fire Training Tower

To improve the fire training facility located on Jones Road a burn structure, pump house, and deflection wall will be constructed within the existing site limits.  This project is funded in part by Measure X.

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org

Program: Municipal Buildings

Current Phase: Construction

Recent Update: The Fire Training Tower has been awarded to Reed Family Enterprises for the Erection of the Fire Training Tower and the Contract has been amended with Fireblast.

Duration: Start October 2018, with target completion of May 2022.


JLRC Park Study

This project will assess the feasibility of improvements that could be implemented at the John Landes Community Center.

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org

Project #: CIP21-00011

Program: Parks

Current Phase: Study

Recent Update: A staff member has been recruiting and working on finalizing recruiting of iterns that will assist in performing the public outreach.

Duration: Began November 2021, target completion of Fall 2022


Joe Balderamma Park Restroom Design

Design for existing restroom facility.

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org

Project #: CIP21-00018

Program: Parks

Current Phase: Design

Recent Update: Discussing potential options for the restroom.

Duration: Start October 2021, with target duration of Summer 2022


LAC Detention Basin at Rancho Del Oro (RDO) 

Loma Alta Creek Detention Basin at Rancho Del Oro, which will be east of Rancho Del Oro and south of Oceanside Boulevard, is planned to alleviate downstream flooding along Loma Alta Creek.

Project Manager: Jonathan Smith, (760) 435-3518 or JGSmith@oceansideca.org

Project #: CIP11-00019

Program: Drainage

Current Phase: Design

Recent Update: CIP Engineering met with CIP Water Utilities. It was determined that Water Utilities would move forward with their Sewer Liner Relocation project and obtain the necessary permits. CIP engineering will hold on the detention basin project until funds are made available for construction.

Duration: Project Start September 2011, with target completion of Spring 2026 (Pending Funding)


Loma Alta Bike Trail

Project Manager: TBD

Project #: TBD

Program: Parks

Current Phase: Under Review


Mance Buchanan Field Lights

Sports Field lighting to be added to the other half of Mance Buchanan park.

Project Manager: Kymberly Laubach, (760) 435-3534, klaubach@oceansideca.org

Project #: CIP21-00013

Program: Parks

Current Phase: Design

Recent Update: A project kick-off with the awarded consultant, REC, was conducted for the amendment of the MND (CEQA Documents). The Cooperative Purchase Agreement with Musco Lighting has been approved for use by the City Attorney.

Duration: Start March 2021, target completion of Summer 2022


Melrose Heights Widening

Study and acquire rights of way for widening Melrose Drive at College/Bobier. Developer to construct the widening.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP19-00009

Program: Thoroughfare-Signals

Current Phase: Monitoring

Recent Update: CIP and Property Management staff continued to coordinate land acquisition and temporary construction easements .

Duration: Project Start October 2019, with target completion TBD


Oceanside Blvd 20A Undergrounding

Undergrounding of utilities within the vicinity of Crouch/Oceanside Blvd. construction and design by SDGE.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP15-00018

Program: Miscellaneous City Capital

Current Phase: Design

Recent Update: Met with SDG&E Governmental Liaison. Discussed extent of project and latest resolution.

Duration: Project Start February 2015 with target completion of Early 2023


OPD HQ Expansion/Relocation Study

Perform study to determine what expansion needs are necessary and assess the future, long term potential for relocation options (if necessary) for the Oceanside Police Department Headquarters.

Project Manager: Brian Thomas, (760) 435-5074 or BThomas@oceansideca.org

Project #: CIP19-00018

Program: Measure X

Current Phase: PSR

Recent Update: Phase 1: Needs Assessment draft report is being reviewed.

Duration: Project Began October 2019, with target completion of late Spring 2021


Pickleball Courts Phase 1

Finalize design and construction of additional courts at Melba Bishop Park.

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org

Project #: CIP21-00009

Program: Parks

Current Phase: Construction

Recent Update: The project has been advertised for construction.

Duration: Began May 2021, with target completion of Winter 2021/2022


Pier View Way Bridge & Lifeguard Headquarters

Please visit the Pier View Bridge and Lifeguard Headquarters webpage for more details and information.

Preliminary design for the restoration of the concrete bridge connecting Pacific Street (bluff) to the Oceanside Pier.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP19-00011

Program: Measure X

Current Phase: Design

Recent Update: Received initial informal historical society support for replacement over restoration. Incorporate public feedback into schematic design.

Duration: Project Start October 2019, with target completion of Spring 2026  


South The Strand Resurfacing Project

Proposed work generally includes: removal and replacement of pedestrian access ramps at intersections; removal and replacement of damaged concrete walks and driveways; replacement of damaged or missing curbs; sawcutting; milling portions of the existing concrete surface and placement of asphalt concrete within the milled area (resurfacing); adjustment of surface utilities; and replacement of traffic striping and marking.

Personnel and equipment will be operating from 8am to 4:30pm, Monday through Friday. While construction is actively taking place, vehicle and pedestrian traffic on South the Strand will either be limited or not allowed. Please follow signage and posted notifications accordingly.

South The Strand is currently scheduled to be closed to traffic, during working hours, for approximately 3 days in the first week of May 2022 while the milling and resurfacing work is performed.

Contact: (760) 435-3569 or www.publicstuff.com

Project #: CIP21-00003

Program: SB-1, Measure X

Current Phase: Construction

Recent Update: Milling of the existing concrete surface and resurfacing with asphalt pavement is schedule to begin Monday 5/2 and will require approximately 3-days to complete.
Seagaze, Wisconsin and South The Strand will be closed to through traffic, bikes and pedestrians during construction. Please plan accordingly and limit use of these roadways during this major construction activity.

Duration: April 11, 2022 to May 13, 2022


 

Street Monument Preservation

Preservation of survey monuments in City of Oceanside.

Project Manager: Bill Tuck, (760) 435-5170 or BTuck@oceansideca.org

Project #: CIP20-00016

Program: SB-1 

Duration: Ongoing Project As-Needed


Thunder Drive Road Rehabilitation

Road improvements for Thunder Drive.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP20-00014

Program: SB-1

Current Phase: Under Review

Recent Update: This project requires coordination with a private property owner/ developer. The developers project is temporarily suspended as a result of Covid- 19. Therefore the project is on hold.

Duration: Began December 2020, with target completion TBD


Storm Drain Improvements

Installation of new storm drain facilities including devices required to comply with the State Trash amendment. Replacement of failing CMP pipes throughout the City.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP19-00021

Program: SB-1

Current Phase: PSR

Recent Update: With the exception of a few materials still awaiting shipping, contractor has completed the installation of the trash capture devices.

Duration: Ongoing on Annual Basis


South Strand Rehabilitation Study

Study for improvements on South Strand.  

Project Manager: Randall Bliss (consultant), (949) 536-2511 or randall.bliss@weareharris.com

Project #: CIP19-00016

Program: Measure X

Current Phase: Construction

Recent Update: Prepare change order to incorporate The Strands surface restoration into the Overlay contract.

Duration: Began October 2019, with target completion of Winter 2021 for Resurfacing and Spring 2022 for Study


Street Market Bollards

Construction of removable street bollards for downtown markets.

Project Manager: A.J. Bartleet, (760) 435-3568 or ABartleet@oceansideca.org

Project #: CIP20-00007

Program: Miscellaneous City Capital

Current Phase: Design

Recent Update: Trial of Anti-Vehicle Barriers at market complete. Reviewing results and discussing options, logistics, and costs.

Duration: Began September 2020, with target completion of Spring 2022  


Tyson Bluffs

Improvements for Tyson Bluffs.

Project Manager: Jonathan Smith, (760) 435-3518 or JGSmith@oceansideca.org

Project #: CIP20-00008

Current Phase: Construction

Duration: Project Start December 2020, with target completion of Spring 2022