CIP Current Projects

ADA Ramp Replacement/Sidewalk In-Fill

New sidewalk, curb and gutter, and pedestrian ramps at various locations throughout the City. One new location has been specifically identified for improvements: (Grandview).

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project#: CIP17-00006

Program: Transnet

Current Phase: Design

Recent Update: Staff has replaced all ADA public notice signs at all known locations. Rough draft of RFP to obtain consulting help in preparing the self-evaluation and transition plans was completed. Rough draft of ADA grievance form to be placed online was complete.

Duration: Began April 2017


ADA for Overlay

ADA Concrete work associated with the Annual Overlay Project includes replacement of non-conforming ramps directly adjacent to proposed asphalt paving work. A separate construction contract will be awarded in advance of the overlay project and all ramp reconstructions will be completed by the time the overlay contract begins.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP19-00020

Program: SB-1

Current Phase: Design

Recent Update: Completed the ADA improvements for the various locations of the overlay project. Completed the ADA improvements for the Rancho Hermosa and Industry Street full depth reclamation (FDR) areas.

Duration: Began October 2019 with target completion of 2021


Annual Overlay

The project provides asphalt overlay of City streets.  Street selections are made based on computerized pavement management system information, staff's review to determine the high priorities for restoration, and citizen's reports of deteriorating street conditions.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project#: CIP19-00013

Program: SB-1

Current Phase: Construction

Recent Update: Finished adjusting utilities on recently paved streets.

Duration: Began October 2019, with target completion 2021


Annual Slurry Seals

Road Repairs: potholes/slurry seals.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP19-00014

Program: SB-1

Current Phase: Construction

Recent Update: Slurry seal operations are 100% complete.

Duration: Began October 2019, with target completion of 2021


Annual Storm Drain Maintenance

Installation of new storm drain facilities including devices required to comply with the State Trash amendment. Replacement of failing CMP pipes throughout the City.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP19-00021

Program: SB-1

Current Phase: PSR

Recent Update: Bid documents to replace storm drain at Woodbine Place were complete and project was bid out. Bids were received and a lowest responsive and responsible bidder was selected. Property management is helping complete the temporary construction easement for the project. Contractor mailed contract documents to be reviewed by City.
Installation of the RRFBs and LED Stop signs was complete.

Duration: Start October 2019, with target completion of 2021


Beachfront Improvements

Please visit the Beachfront Improvements page for more details and updates.

New construction and building renovations to include various City beach operations and public facilities within the Pier Amphitheater area.

Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org

Project #: CIP19-00023

Program: Municipal Buildings

Current Phase: Construction

Recent Update: Continued construction of the new Lift Station, maintenance building and bath house restoration. The contractor started stairway demolition and the Pacific utility work. Staff prepared a staff report for contract change order 4 and expediting phase 1 completion (to open the stairway and plaza to the public in Spring 2021). The Strand reopened to the public.

Duration: Began April 2020, with target completion of Winter 2021


Buccaneer Beach restroom

Design for new beach restroom facility at Buccaneer Park.

Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org

Project #: CIP19-00017

Program: Measure X

Current Phase: PSR

Recent Update: Planning division, Parks and Rec and Public Works departments and City of Carlsbad Parks and Rec department reviewed and scored five proposals (RFPs).

Duration: Began October 2019, with target completion of April 2021


Buccaneer Park Facilities Study

This is a project study review of the aging facilities at Buccaneer Park. Recommendations will contain funding requirements for improvements. Remodel of the park restroom, picnic facility and other park amenities.

Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org

Project #: CIP11-00055

Program: Parks

Current Phase: PSR

Recent Update: Planning division, Parks and Rec and Public Works departments and City of Carlsbad Parks and Rec department reviewed and scored five proposals (RFPs).

Duration: Began October 2011, target completion of April 2021


Citywide Traffic Signal Upgrades HSIP 2019

Various signal improvements.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP20-00002

Program: Grant

Current Phase: Under Review

Recent Update: Prepared a draft RFP for consultant services to prepare plans, specifications, and estimates.

Duration: Began May 2020


Civic Center Fuel Storage

Installation of a new fuel tank for the civic center generator.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP18-00016

Program: Municipal Buildings

Current Phase: Design

Recent Update: Notified the Consultant of the comments received by the various departments.

Duration: Start October 2018, with target completion of 2021


Cleveland Storm Drain

Upgrade of storm drain. Cleveland from Seagaze to Surfrider and Surfrider to the Ocean. May include parallel line from Civic Center to Surfrider.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP17-00007

Program: Drainage

Current Phase: Design

Recent Update: Project progress pending NCTD utility crossing agreement approval and Coastal Commission jurisdiction determination.

Duration: Start June 2017, with target completion of December 2021


Coast Highway Bridge Replacement

This is a Federally funded project to replace the bridge that carries Coast Hwy over the San Luis Rey River. Caltrans will be the partner agency, with financing through the HBRRP (Highway Bridge Rehabilitation and Replacement Program.)

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP11-00030

Program: Transnet

Current Phase: Design

Recent Update: Boring locations are on City property. Staff reevaluated access to boring location in an attempt to eliminate need or permission to access private properties.

Duration: Start September 2011, with target completion of April 2023


Coast Highway Corridor Design

Project to install separated bike lanes between Oceanside Boulevard and Morse Street.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP20-00012

Program: Transnet

Current Phase: Under Review

Recent Update: Staff is preparing a draft RFP for consultant services to prepare plans, specifications, and estimates for a phased project.

Duration: Began October 2020


Coastal Rail Trail Design

Project for the design of the Coastal Rail Trail for the section between Oceanside Blvd and Morse Street.

Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org

Project #: CIP16-00011

Program: Transnet

Current Phase: Design

Recent Update: Planning division, Parks and Rec and Public Works departments and City of Carlsbad Parks and Rec department reviewed and scored five proposals (RFPs).

Duration: Began August 2016, target completion of June 2021


College Between Vista & Old Grove Construction

Improvements for College Boulevard.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP20-00013

Program: Thoroughfare

Current Phase: Under Review

Duration: Began December 2020


College Between Waring & Old Grove Design

Thoroughfare Widening project - Corridor Right-of-way improvements to provide congestion relief.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP19-00019

Program: Thoroughfare

Current Phase: Design

Recent Update: Prepared draft RFP for design services.

Duration: Began December 2020, target completion of June 2022


Douglas Bridge Seismic Retrofit

This is a federally funded project to retrofit the bridge that carries Douglas Drive over the San Luis Rey River to meet earthquake design standards.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP11-00010

Program: Transnet

Current Phase: Design

Recent Update: City consultant submitted retrofit strategy and geotechnical calculations for Caltrans HQ review approval of retrofit limited to above-ground structure elements.

Duration: Start September 2011, with target completion of August 2023

 


Douglas Drive Median

Median on Douglas Dr between 300 feet south of Westport Dr and 250 feet north of Festival Drive.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP16-00010

Program: Transnet

Current Phase: Design

Recent Update: While the project is out to bid staff answered bidders questions and prepared and posted project addendum.

Duration: Start August 2016, with target completion of July 2021


El Corazon Aquatic Center

Please visit the El Corazon Aquatic Center page for more details and updates.

Development of a new aquatics center adjacent to the El Corazon Senior Center.  The project includes administration, locker-room and equipment facility buildings, a new shared multi-purpose hall,  a 56-meter competition pool, educational pool, splash pad and outdoor event areas.

Project Manager: Brian Thomas, (760) 435-5074 or BThomas@oceansideca.org

Project #: CIP15-00020

Program: Municipal Buildings

Current Phase: Construction

Recent Update: Fit and Finish work continues. Site work in nearing completion as well. The Splash Pad construction is nearing completion.

Duration: Start April 2015, with target completion of early 2021


Fire Mountain Utility Undergrounding

City participation in a "Section 20B" underground utility conversion with Eternal Hills Cemetery to remove overhead poles and wires along Fire Mountain between El Camino Real and the City reservoir.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP13-00017

Program: Miscellaneous City Capital

Current Phase: Design

Recent Update: Met with SDG&E Governmental Liaison to discuss status of project. Obtained latest design from SDG&E.

Duration: Project Start August 2013


Fiber Optic to Fire Station No. 6

Replacement of the current microwave radio signal, susceptible to wind movement and tree growth into its line of sight, with fiber optic system to provide network stability.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP19-00015

Program: Miscellaneous City Capital

Current Phase: On-Hold

Recent Update: Sent an RFP to contractor working on Traffic Signal at San Ramon and RDO to obtain the cost to run conduit across two intersections and perform an inspection of existing conduit that runs between COC and Fire Station #6.

Duration: Project Start October 2019


Fire Station No1/EOC Design

Measure X funds contribution toward design of a new Fire Station #1 at 602 Civic Center Drive which will require relocation of Code Enforcement offices.

Project Manager: Brian Thomas, (760) 435-5074 or BThomas@oceansideca.org

Project #: CIP19-00012

Program: Measure X

Current Phase: Design

Recent Update: Staff has received 50% construction documents for review as well as specifications, etc. The PM will be working with Planning to initiate the CUP process this week.

Duration: Start October 2019, with target completion of November 2022


Fire Station #4 Rehabilitation Phase 2

Repair deficiencies in the sleeping quarters, showers, bathrooms and hallways not addressed as part of Phase 1 improvements.

Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org

Project #: CIP19-00024

Program: Municipal Buildings

Current Phase: Under Review

Recent Update: A meeting with the Fire Chief, Deputy Fire Chief, City Engineer, Principal Civil Engineer and the Maintenance Supervisor was held to define the scope of work for phase 2.

Duration: Project Began October 2019


Fire Training Tower

To improve the fire training facility located on Jones Road a burn structure, pump house, and deflection wall will be constructed within the existing site limits.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP18-00008

Program: Municipal Buildings

Current Phase: Construction

Recent Update: Revised building plans submitted to and approved by Building Department. Engineer of Record attempted to revise approved plan by revising shop drawing details. Engineer of record rescinded proposed revise in response to staff's request for explanation of the revise and associated construction cost increase.

Duration: Start October 2018, with target completion of March 2021


JLRC Park Study

Project Manager: TBD

Project #: TBD

Program: Parks

Current Phase: Under Review


LAC Detention Basin at Rancho Del Oro (RDO)

Loma Alta Creek Detention Basin at Rancho Del Oro, which will be east of Rancho Del Oro and south of Oceanside Boulevard, is planned to alleviate downstream flooding along Loma Alta Creek.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP11-00019

Program: Drainage

Current Phase: Design

Recent Update: CIP Engineering met with CIP Water Utilities. It was determined that Water Utilities would move forward with their Sewer Liner Relocation project and obtain the necessary permits. CIP engineering will hold on the detention basin project until funds are made available for construction.

Duration: Project Start September 2011


Loma Alta Bike Trail

Project Manager: TBD

Project #: TBD

Program: Parks

Current Phase: Under Review


Mance Buchanan Field Lights

Project Manager: TBD

Project #: TBD

Program: Parks

Current Phase: Under Review


Melrose Heights Widening

Study and acquire rights of way for widening Melrose Drive at College/Bobier. Developer to construct the widening.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP19-00009

Program: Thoroughfare-Signals

Current Phase: Monitoring

Recent Update: Coordinated with Property Management staff on survey data to acquire small portion of County land.

Duration: Project Start October 2019


Oceanside Blvd 20A Undergrounding

Undergrounding of utilities within the vicinity of Crouch/Oceanside Blvd. construction and design by SDGE.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP15-00018

Program: Miscellaneous City Capital

Current Phase: Design

Recent Update: Met with SDG&E Governmental Liaison. Discussed extent of project and latest resolution.

Duration: Project Start February 2015 with target completion of Early 2023


OPD HQ Expansion/Relocation Study

Perform study to determine what expansion needs are necessary and assess the future, long term potential for relocation options (if necessary) for the Oceanside Police Department Headquarters.

Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org

Project #: CIP19-00018

Program: Measure X

Current Phase: PSR

Recent Update: Initial data collection by consultant complete.

Duration: Project Began October 2019, with target completion of April 2021 


Pickleball Courts Phase 1

Project Manager: TBD

Project #: TBD

Program: Parks

Current Phase: Under Review


Pier Rehab-Concrete Design

Preliminary design for the restoration of the concrete bridge connecting Pacific Street (bluff) to the Oceanside Pier.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP19-00011

Program: Measure X

Current Phase: Design

Recent Update: Continued to prepare Staff Report for revised scope of now phased design. First phase is gathering stakeholder needs and determine historic and coastal project constraints to more accurately scope and price final design.

Duration: Project Start October 2019


Railroad Crossing Saftey Improvements

Please visit the Quiet Zone Update page for more details and updates.

Construction of safety-related improvements at the five at-grade railroad crossings in the coastal rail trail corridor. The specific crossings are Surfrider Avenue, Mission Avenue, Wisconsin Street, Oceanside Blvd, and Cassidy Street.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP14-00013

Program: Transnet

Current Phase: Construction

Recent Update: Warning device installed and gate relocated for new Mission to OTC walkway. Site Coordination meeting held with City contractor Balfour Beatty and OBR contractor DPR for the traffic signal installation at Mission/Myers intersection.

Duration: Project Start October 2014, with target completion of February 2021


Street Monument Preservation

Preservation of survey monuments in City of Oceanside.

Project Manager: Bill Tuck, (760) 435-5170 or BTuck@oceansideca.org

Project #: CIP20-00016

Program: SB-1

Current Phase: Under Review

Duration: Project Start December 2020


Thunder Drive Road Rehabilitation

Road improvements for Thunder Drive.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP20-00014

Program: SB-1

Current Phase: Under Review

Recent Update: This project requires coordination with a private property owner/ developer. The developers project is temporarily suspended as a result of Covid- 19. Therefore the project is on hold.

Duration: Began December 2020


Storm Drain Improvements

Installation of new storm drain facilities including devices required to comply with the State Trash amendment. Replacement of failing CMP pipes throughout the City.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP19-00021

Program: SB-1

Current Phase: PSR

Recent Update: Bid documents to replace storm drain at Woodbine Place were complete and project was bid out. Bids were received and a lowest responsive and responsible bidder was selected. Property management is helping complete the temporary construction easement for the project. Contractor mailed contract documents to be reviewed by City.
Installation of the RRFBs and LED Stop signs was complete.

Duration: Began October 2019


South Strand Rehabilitation Study

Study for improvements on South Strand.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP19-00016

Program: Measure X

Current Phase: Monitoring

Recent Update: KDM continues to work on the topographic survey of the strand.
Met with Penhall to obtain a proposal for a grind and mill temporary solution to the road along the strand.

Duration: Began October 2019


Street Market Bollards

Construction of removable street bollards for downtown markets.

Project Manager: A.J. Bartleet, (760) 435-3568 or ABartleet@oceansideca.org

Project #: CIP20-00007

Program: Miscellaneous City Capital

Current Phase: Design

Recent Update: Preliminary budget prepared.

Duration: Began September 2020, with target completion of summer 2021


Traffic Signal @ RDO/San Ramon

New Traffic Signal improvement located at RDO & San Ramon.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP19-00006

Program: Thoroughfare-Signals

Current Phase: Construction

Recent Update: SDG&E installed the meter which will power the traffic signal. All conduit was installed and wired pulled through it. All poles were installed with their respective gear. Asphalt work at Rancho Del Oro was complete. Project is complete pending the completion of the punch list items.

Duration: Began October 2019, with target completion of January 2021


Tyson Bluffs

Improvements for Tyson Bluffs.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP20-00008

Current Phase: Construction

Duration: Project Start December 2020