CIP Current Projects

ADA Ramp Replacement/Sidewalk In-Fill

New sidewalk, curb and gutter, and pedestrian ramps at various locations throughout the City. One new location has been specifically identified for improvements: (Grandview).

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project#: CIP17-00006

Program: Transnet

Current Phase: Design

Recent Update: Staff has replaced all ADA public notice signs at all known locations. Rough draft of RFP to obtain consulting help in preparing the self-evaluation and transition plans was completed. Rough draft of ADA grievance form to be placed online was complete.

Duration: Began April 2017


ADA Municipal Buildings Assessment

In keeping with its ongoing efforts to serve all members of the public, the City of Oceanside is updating its Americans with Disabilities Act (ADA) transition plan and self-evaluation. The accessibility plan provides a comprehensive plan for accessibility for persons with disabilities to City facilities, programs, services, and events. 

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project#: CIP21-00014

Program:

Current Phase: In-Process

Duration: Project began August 2021, with anticipated finish in August 2022.

Recent Update: The City is seeking input from the community and organizations assisting people with disabilities. Your feedback will assist in addressing and prioritizing current and future accessibility needs. The surveys are open for input until November 30, 2021 and includes a drop-down menu to take in several languages.

Link to Online Survey:

Survey for public input

Survey for Organizations Representing People with Disabilities

Your comments and opinions are important to us and will provide valuable information regarding how the City can better serve those with disabilities.  Thank you for your time!

Link to More ADA Information

City of Oceanside ADA information and contact


ADA for Overlay

ADA Concrete work associated with the Annual Overlay Project includes replacement of non-conforming ramps directly adjacent to proposed asphalt paving work. A separate construction contract will be awarded in advance of the overlay project and all ramp reconstructions will be completed by the time the overlay contract begins.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP21-00003

Program: SB-1

Current Phase: Construction

Recent Update: Project is currently under construction. 

Duration: Began July 2021 and estimated completion date is September 2021


Alex Road Skatepark Improvement

Facility Improvements including a new restroom facility and drinking fountain.

Project Manager: Kymberly Laubach, (760) 435-3534 or KLaubach@oceansideca.org

Project #: CIP21-00017

Program: Parks

Current Phase: Design

Recent Update: The design and construction of the Green Flush Restroom is in-progress. Staff is in-progress to obtain design documents to prepare the site for the restroom.

Duration: Begin August 2021 and estimated completion date is July 2022

 

Annual Overlay FY19-20

The project provides asphalt overlay of City streets. All FY19-20 project locations are complete except for Mission Avenue from approximately Clementine to I-5. This portion of the project is currently underway. Work will be performed at night; Sundays starting at 9:00pm to Friday mornings at 5:00am.  This project is funded in part by Measure X.

FY19-20 Overlay and Slurry Seal Location Exhibits

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project#: CIP19-00013

Program: SB-1

Current Phase: Construction

Recent Update: Lowered utilities on Mission Avenue.

Duration: Anticipated to be completed end of May 2021


Annual Overlay FY20-21

The project provides asphalt overlay of City streets.  Street selections are made based on computerized pavement management system information, staff's review to determine the high priorities for restoration, and citizen's reports of deteriorating street conditions.  This project is funded in part by Measure X.

FY20-21 Overlay and Slurry Seal Location Exhibits

Full Depth Reclamation (FDR) Process:

https://www.youtube.com/watch?v=c-oMzqB0MS0

https://www.youtube.com/watch?v=mWtDOB5n7tI

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project#: CIP21-00003

Program: SB-1, TransNet, Measure X

Current Phase: Construction.

Recent Update: Project is currently under construction.

Duration: Work Commenced July 2021 and estimated completion date is September 2021.


Annual Slurry Seal FY20-21

Road Repairs: potholes/slurry seals.  This project is funded in part by Measure X.

Slurry Seal Locations Map and Schedule (Updated for 10-25-2021 to 11-05-2021)

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP21-00002

Program: SB-1, Trans Net, Measure X

Current Phase: Construction

Recent Update: Crack Sealing at various locations is currently in progress. Application of Slurry Seals is schedule to begin October 14, 2021 per the attached schedules and maps.
Construction generally includes: Traffic control and notifications; Crack routing and Sealing; application of Type II Slurry Seals; Street Sweeping; and replacement of Traffic Striping and Pavement Markings.

Duration: End of September through the end of November 2021.


Annual Storm Drain Maintenance

Installation of new storm drain facilities including devices required to comply with the State Trash amendment. Replacement of failing CMP pipes throughout the City.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP19-00021

Program: SB-1

Current Phase: PSR

Recent Update: Bid documents to replace storm drain at Woodbine Place were complete and project was bid out. Bids were received and a lowest responsive and responsible bidder was selected. Property management is helping complete the temporary construction easement for the project. Contractor mailed contract documents to be reviewed by City.
Installation of the RRFBs and LED Stop signs was complete.

Duration: Start October 2019, with target completion of 2021


Beachfront Improvements

Please visit the Beachfront Improvements page for more details and updates.

New construction and building renovations to include various City beach operations and public facilities within the Pier Amphitheater area.  This project is funded in part by Measure X.

Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org

Project #: CIP19-00023

Program: Municipal Buildings

Current Phase: Construction

Recent Update: Work completed during the past year includes the relocation of the sewage lift station and utilities, construction of a new staircase from Pacific Street down to the plaza and The Strand, and new seating, pavers, and landscaping in the plaza. Masonry walls of the new restroom facilities have been erected. Construction of the restrooms, police substation, and maintenance building continue.

Duration: Began April 2020, with target completion of Winter 2021


Beachfront Improvement Feasibility Study - Phase 2

Please visit the Beachfront Improvements Feasibility Study - Phase 2 webpage for more details and updates.

Phase II of the Beachfront Improvement Feasibility Study explores potential improvements to the Junior Seau Beach Community Center, Junior Seau Pier Amphitheater/ Bandshell, and the pier plaza and public spaces in between.

Project Manager: Darra Woods, (760) 435-5094 or Dwoods@oceansideca.org

Project #: CIP21-00006

Program: Community Facilities

Current Phase: Study

Recent Update: Please visit the Beachfront Improvement Feasibility Study – Phase II page for more details and updates.

Duration: Began February 2021, with target completion of January 2022


Buccaneer Beach restroom

Design for new beach restroom facility at Buccaneer Park.  This project is funded in part by Measure X.

Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org

Project #: CIP19-00017

Program: Measure X

Current Phase: PSR

Recent Update: Planning division, Parks and Rec and Public Works departments and City of Carlsbad Parks and Rec department reviewed and scored five proposals (RFPs).

Duration: Began October 2019, with target completion of April 2021


Buccaneer Park Facilities Study

This is a project study review of the aging facilities at Buccaneer Park. Recommendations will contain funding requirements for improvements. Remodel of the park restroom, picnic facility and other park amenities.  This project is funded in part by Measure X.

Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org

Project webpage: Buccaneer Park Improvements

Project #: CIP11-00055

Program: Parks

Current Phase: PSR

Recent Update: Planning division, Parks and Rec and Public Works departments and City of Carlsbad Parks and Rec department reviewed and scored five proposals (RFPs).

Duration: Began October 2011, target completion of April 2021


Calavera Creek Crossing Design

Modernization and Improvements for areas within Calavera Creek

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org

Project #: CIP21-00010

Program: Parks

Current Phase: Design

Recent Update: Based on available funds, the project scope has changed and the City is in-progress to get a consultant to prepare design documents for the new project scope.

Duration: Start November 2021, with target completion of Fall 2022.


Citywide Traffic Signal Upgrades HSIP 2019

Various signal improvements.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP20-00002

Program: Grant

Current Phase: Under Review

Recent Update: Prepared a draft RFP for consultant services to prepare plans, specifications, and estimates.

Duration: Began May 2020


Civic Center Fuel Storage 

Installation of a new fuel tank for the civic center generator.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP18-00016

Program: Municipal Buildings

Current Phase: Design

Recent Update: Notified the Consultant of the comments received by the various departments.

Duration: Start October 2018, with target completion of 2021


Cleveland Storm Drain 

Upgrade of storm drain. Cleveland from Seagaze to Surfrider and Surfrider to the Ocean. May include parallel line from Civic Center to Surfrider.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP17-00007

Program: Drainage

Current Phase: Design

Recent Update: Project progress pending NCTD utility crossing agreement approval and Coastal Commission jurisdiction determination.

Duration: Start June 2017, with target completion of December 2021


Coast Highway Bridge Replacement

This is a Federally funded project to replace the bridge that carries Coast Hwy over the San Luis Rey River. Caltrans will be the partner agency, with financing through the HBRRP (Highway Bridge Rehabilitation and Replacement Program.)

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP11-00030

Program: Transnet

Current Phase: Design

Recent Update: Boring locations are on City property. Staff reevaluated access to boring location in an attempt to eliminate need or permission to access private properties.

Duration: Start September 2011, with target completion of April 2023


Coast Highway Corridor Design

Project to install separated bike lanes between Oceanside Boulevard and Morse Street.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP20-00012

Program: Transnet

Current Phase: Under Review

Recent Update: Staff is preparing a draft RFP for consultant services to prepare plans, specifications, and estimates for a phased project.

Duration: Began October 2020


Coastal Rail Trail Design 

Project for the design of the Coastal Rail Trail for the section between Oceanside Blvd and Morse Street.

Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org

Project #: CIP16-00011

Program: Transnet

Current Phase: Design

Recent Update: Planning division, Parks and Rec and Public Works departments and City of Carlsbad Parks and Rec department reviewed and scored five proposals (RFPs).

Duration: Began August 2016, target completion of June 2021


College Between Vista & Old Grove Construction

Improvements for College Boulevard.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP20-00013

Program: Thoroughfare

Current Phase: Under Review

Duration: Began December 2020


College Between Waring & Old Grove Design

Thoroughfare Widening project - Corridor Right-of-way improvements to provide congestion relief.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP19-00019

Program: Thoroughfare

Current Phase: Design

Recent Update: Prepared draft RFP for design services.

Duration: Began December 2020, target completion of June 2022


Dog Facilities Study

This project seeks to determine which parks can best accommodate Dog Facilities within the City.

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org

Project #: CIP21-00010

Program: Parks

Current Phase: Study

Recent Update: Preparation of the Final Dog Facilities Study is in-progress. 

Duration: Start May 2021, with target completion of Winter 2021


Douglas Bridge Seismic Retrofit

This is a federally funded project to retrofit the bridge that carries Douglas Drive over the San Luis Rey River to meet earthquake design standards.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP11-00010

Program: Transnet

Current Phase: Design

Recent Update: City consultant submitted retrofit strategy and geotechnical calculations for Caltrans HQ review approval of retrofit limited to above-ground structure elements.

Duration: Start September 2011, with target completion of August 2023


Douglas Drive Median

Median on Douglas Dr between 300 feet south of Westport Dr and 250 feet north of Festival Drive.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP16-00010

Program: Transnet

Current Phase: Design

Recent Update: While the project is out to bid staff answered bidders questions and prepared and posted project addendum.

Duration: Start August 2016, with target completion of July 2021


El Corazon Aquatic Center

Please visit the El Corazon Aquatic Center page for more details and updates.

Development of a new aquatics center adjacent to the El Corazon Senior Center.  The project includes administration, locker-room and equipment facility buildings, a new shared multi-purpose hall,  a 56-meter competition pool, educational pool, splash pad and outdoor event areas.

Project Manager: Brian Thomas, (760) 435-5074 or BThomas@oceansideca.org

Project #: CIP15-00020

Program: Municipal Buildings

Current Phase: Construction

Recent Update: Fit and Finish work continues. Site work in nearing completion as well. The Splash Pad construction is nearing completion.

Duration: Start April 2015, with target completion of early 2021


Fire Mountain Utility Undergrounding

City participation in a "Section 20B" underground utility conversion with Eternal Hills Cemetery to remove overhead poles and wires along Fire Mountain between El Camino Real and the City reservoir.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP13-00017

Program: Miscellaneous City Capital

Current Phase: Design

Recent Update: Met with SDG&E Governmental Liaison to discuss status of project. Obtained latest design from SDG&E.

Duration: Project Start August 2013


Fiber Optic to Fire Station No. 6

Replacement of the current microwave radio signal, susceptible to wind movement and tree growth into its line of sight, with fiber optic system to provide network stability.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP19-00015

Program: Miscellaneous City Capital

Current Phase: On-Hold

Recent Update: Sent an RFP to contractor working on Traffic Signal at San Ramon and RDO to obtain the cost to run conduit across two intersections and perform an inspection of existing conduit that runs between COC and Fire Station #6.

Duration: Project Start October 2019


Fire Station No1/EOC Design

Measure X funds contribution toward design of a new Fire Station #1 at 602 Civic Center Drive which will require relocation of Code Enforcement offices.

Project Manager: Brian Thomas, (760) 435-5074 or BThomas@oceansideca.org

Project #: CIP19-00012

Program: Measure X

Current Phase: Design

Duration: Start October 2019, with target completion of November 2022

Recent Update: A Public meeting is set for October 21, 2021, from 6:00 p.m. to 9:00 p.m. in the City Council Chambers to discuss the project and to answer as many questions as possible. The City’s project Architect, GV Salts of STK Architecture, Inc. will be on hand as will City staff to provide details about the project’s need and the goals of the new fire station.


Fire Station #4 Rehabilitation Phase 2

Repair deficiencies in the sleeping quarters, showers, bathrooms and hallways not addressed as part of Phase 1 improvements.

Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org

Project #: CIP19-00024

Program: Municipal Buildings

Current Phase: Under Review

Recent Update: A meeting with the Fire Chief, Deputy Fire Chief, City Engineer, Principal Civil Engineer and the Maintenance Supervisor was held to define the scope of work for phase 2.

Duration: Project Began October 2019


Fire Training Tower

To improve the fire training facility located on Jones Road a burn structure, pump house, and deflection wall will be constructed within the existing site limits.  This project is funded in part by Measure X.

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org

 Program: Municipal Buildings

Current Phase: Construction

Recent Update: Staff is in-progress to award the contractor for the construction of the tower.

Duration: Start October 2018, with target completion of May 2022.


JLRC Park Study

This project will assess the feasibility of improvements that could be implemented at the John Landes Community Center.

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org

Project #: CIP21-00011

Program: Parks

Current Phase: Study

Recent Update: Teamed up with library services, the resource center, and parks and recreation. Study will be completed as part of the Landes Community Engagement and Leadership Project. The project is currently in the recruitment phase for a staff member and interns that will assist in performing the public outreach.

Duration: Public Outreach anticipated to start in November 2021.


Joe Balderamma Park Restroom Design

Design for existing restroom facility.

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org

Project #: CIP21-00018

Program: Parks

Current Phase: Design

Recent Update: Discussing potential options for the restroom.

Duration: Start October 2021


LAC Detention Basin at Rancho Del Oro (RDO) 

Loma Alta Creek Detention Basin at Rancho Del Oro, which will be east of Rancho Del Oro and south of Oceanside Boulevard, is planned to alleviate downstream flooding along Loma Alta Creek.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP11-00019

Program: Drainage

Current Phase: Design

Recent Update: CIP Engineering met with CIP Water Utilities. It was determined that Water Utilities would move forward with their Sewer Liner Relocation project and obtain the necessary permits. CIP engineering will hold on the detention basin project until funds are made available for construction.

Duration: Project Start September 2011


Loma Alta Bike Trail

Project Manager: TBD

Project #: TBD

Program: Parks

Current Phase: Under Review


Mance Buchanan Field Lights

Project Manager: Kymberly Laubach, (760) 435-3534, klaubach@oceansideca.org

Project #: CIP21-00013

Program: Parks

Current Phase: Design

Recent Update: Work in progress on amendment to environmental documentation (i.e. CEQA). Geotechnical Report in-progress.

Duration: Start March 2021, target completion of Summer 2022


Melrose Heights Widening

Study and acquire rights of way for widening Melrose Drive at College/Bobier. Developer to construct the widening.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP19-00009

Program: Thoroughfare-Signals

Current Phase: Monitoring

Recent Update: Coordinated with Property Management staff on survey data to acquire small portion of County land.

Duration: Project Start October 2019


Oceanside Blvd 20A Undergrounding

Undergrounding of utilities within the vicinity of Crouch/Oceanside Blvd. construction and design by SDGE.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP15-00018

Program: Miscellaneous City Capital

Current Phase: Design

Recent Update: Met with SDG&E Governmental Liaison. Discussed extent of project and latest resolution.

Duration: Project Start February 2015 with target completion of Early 2023


OPD HQ Expansion/Relocation Study

Perform study to determine what expansion needs are necessary and assess the future, long term potential for relocation options (if necessary) for the Oceanside Police Department Headquarters.

Project Manager: Mahsima Mohammadi, (760) 435-3548 or MMohammadi@oceansideca.org

Project #: CIP19-00018

Program: Measure X

Current Phase: PSR

Recent Update: Initial data collection by consultant complete.

Duration: Project Began October 2019, with target completion of April 2021 


Pickleball Courts Phase 1

Finalize design and construction of additional courts at Melba Bishop Park.

Project Manager: Kymberly Laubach, (760) 435-3534 or klaubach@oceansideca.org

Project #: CIP21-00009

Program: Parks

Current Phase: Construction

Recent Update: Staff is in-progress to award contract for the construction of the Pickleball Courts.

Duration: Began May 2021, with target completion of Winter 2021


Pier View Way Bridge & Lifeguard Headquarters

Please visit the Pier View Bridge and Lifeguard Headquarters webpage for more details and information.

Preliminary design for the restoration of the concrete bridge connecting Pacific Street (bluff) to the Oceanside Pier.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP19-00011

Program: Measure X

Current Phase: Design

Recent Update: Continued to prepare Staff Report for revised scope of now phased design. First phase is gathering stakeholder needs and determine historic and coastal project constraints to more accurately scope and price final design.

Duration: Project Start October 2019


Railroad Crossing Saftey Improvements

Please visit the Quiet Zone Update page for more details and updates.

Construction of safety-related improvements at the five at-grade railroad crossings in the coastal rail trail corridor. The specific crossings are Surfrider Avenue, Mission Avenue, Wisconsin Street, Oceanside Blvd, and Cassidy Street.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP14-00013

Program: Transnet

Current Phase: Construction

Recent Update: The City received FRA approval of the Quiet Zone application, including Risk Index Calculation, through Councilman Levin’s Office on June 16.

Duration: Project Start October 2014, with target completion of February 2021


Street Monument Preservation

Preservation of survey monuments in City of Oceanside.

Project Manager: Bill Tuck, (760) 435-5170 or BTuck@oceansideca.org

Project #: CIP20-00016

Program: SB-1

Current Phase: Under Review

Duration: Project Start December 2020


Thunder Drive Road Rehabilitation

Road improvements for Thunder Drive.

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP20-00014

Program: SB-1

Current Phase: Under Review

Recent Update: This project requires coordination with a private property owner/ developer. The developers project is temporarily suspended as a result of Covid- 19. Therefore the project is on hold.

Duration: Began December 2020


Storm Drain Improvements

Installation of new storm drain facilities including devices required to comply with the State Trash amendment. Replacement of failing CMP pipes throughout the City.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP19-00021

Program: SB-1

Current Phase: PSR

Recent Update: Bid documents to replace storm drain at Woodbine Place were complete and project was bid out. Bids were received and a lowest responsive and responsible bidder was selected. Property management is helping complete the temporary construction easement for the project. Contractor mailed contract documents to be reviewed by City.
Installation of the RRFBs and LED Stop signs was complete.

Duration: Began October 2019


South Strand Rehabilitation Study

Study for improvements on South Strand.  

Project Manager: Darra Woods, (760) 435-5094 or DWoods@oceansideca.org

Project #: CIP19-00016

Program: Measure X

Current Phase: Monitoring

Recent Update: KDM continues to work on the topographic survey of the strand.
Met with Penhall to obtain a proposal for a grind and mill temporary solution to the road along the strand.

Duration: Began October 2019


Street Market Bollards

Construction of removable street bollards for downtown markets.

Project Manager: A.J. Bartleet, (760) 435-3568 or ABartleet@oceansideca.org

Project #: CIP20-00007

Program: Miscellaneous City Capital

Current Phase: Design

Recent Update: Investigating logistics of operations.

Duration: Began September 2020, with target completion of Fall 2021


Traffic Signal @ RDO/San Ramon

New Traffic Signal improvement located at RDO & San Ramon.

Project Manager: Victor Velasco, (760) 435-5102 or VVelasco@oceansideca.org

Project #: CIP19-00006

Program: Thoroughfare-Signals

Current Phase: Construction

Recent Update: SDG&E installed the meter which will power the traffic signal. All conduit was installed and wired pulled through it. All poles were installed with their respective gear. Asphalt work at Rancho Del Oro was complete. Project is complete pending the completion of the punch list items.

Duration: Began October 2019, with target completion of January 2021


Tyson Bluffs

Improvements for Tyson Bluffs.

Project Manager: David Toschak, (760) 435-5106 or DToschak@oceansideca.org

Project #: CIP20-00008

Current Phase: Construction

Duration: Project Start December 2020